EverWind Fuels ("EverWind"), a leading North American developer of a green fuels hub centered in Atlantic Canada, announced the completion of Front-End Engineering Design (FEED) and Front-End Loading Engineering (FEL-3) with Black & Veatch for its Phase 1 Green Hydrogen to Green Ammonia project in Point Tupper, Nova Scotia (the “Project”).
The completion of the FEED engineering, which included over 110,000 hours of engineering, marks a major milestone in the development of the Project and represents the first announced completion of FEED for a large-scale green hydrogen and green ammonia production facility in North America.
The Project will use cutting-edge PEM electrolyzers, and ammonia synthesis technology from Casale S.A. to convert water from man-made Landrie Lake and energy primarily from newly-built wind farms into green hydrogen and green ammonia. The first phase of EverWind’s project is designed to produce approximately 240,000 tonnes per annum of green ammonia. The Project meets the strictest global requirements for green fuels set by the European Renewable Energy Directive and has been pre-certified by CertifHy™.
The Project, which is part of EverWind's larger initiative to develop an Atlantic Canadian green fuels hub, will bring significant economic and environmental benefits to the region. Deloitte has performed a socio-economic study analyzing the benefits, some of which have already been realized through development spend and work to-date.
The significant experience, learnings and expertise gained through the FEED process will directly benefit the ongoing development of future phases of the project in Nova Scotia, as well as the concurrent development of a world scale green fuels project in Newfoundland and Labrador.
Point Tupper Green Hydrogen & Green Ammonia Project (Phase 1):
Completion of FEED and Construction Permitting: engineering works began in Q1 2022, advancing over two years to completion of FEED in March 2024. The Project’s environmental assessment approval was received in February 2023, with construction on track to begin later this year, and first production in 2026.
Newly-built, owned and operated wind farms: EverWind and its First Nations partners Membertou, Paqtnkek, and Potlotek, are developing the Windy Ridge, Kmtnuk, and Bear Lake wind farms. Two of the wind farms have received environmental approval and all three are expected to be operational by the end of 2026.
Community Engagement: Community engagement work is ongoing and will continue through the life of the project. EverWind has established a Community Liaison Committee for the Project and is looking to support local communities with cultural programs, youth initiatives, health and wellness, and community development.
Local Jobs Creation: EverWind is currently in discussions with local unions and anticipates working in partnership with unions while providing significant opportunities to both apprentices and First Nations.
EverWind | https://everwindfuels.com/
Black & Veatch | www.bv.com