Shanghai Electric Reports on Dubai 950MW CSP+PV Solar Power Project

Shanghai Electric, as the EPC contractor of Dubai 950MW CSP+PV solar complex, the fourth phase of Mohammad Bin Rashid Al Maktoum Solar Park, made a detailed report on the huge solar power plant during the Press Release in Beijing. The fourth phase of the solar park will use three technologies to produce 950MW of clean energy - 600MW from a parabolic basin complex, 100MW from a solar tower, and 250MW will be generated from photovoltaic panels.

The project was awarded to ACWA consortium on September 16, 2017, and its opening ceremony was held in Dubai on March 19, 2018. Shanghai Electric signed EPC contract with DEWA, ACWA Power on April 13, 2018 in Shanghai, China. The construction has been started since December 21, 2018.

The expected construction duration lasts 48 months, meaning the overall 700MW CSP project will be completed by the end of 2022 in four years. Seperately, the first parabolic trough CSP plant is planned to be operational on August 21, 2021, in 32 months, tower CSP plant finished on November 21, 2021 in 35 months, and the second and third parabolic trough plants to be completed by the end of the year of 2022. 

Free report: Introduction of Dubai 950MW CSP+PV Project by Shanghai Electric

The fourth phase solar project has already achieved many world records:

  • World largest single-site investment project in CSP based on IPP model---USD 4.4 billion
  • World largest capacity of single CSP+PV project---950MW
  • World largest area of single CSP+PV project---44 square kilometers
  • World biggest quantity of molten salt used in single CSP project---550,000 tons
  • World tallest CSP tower---260m
  • World leading tower wireless heliostat technology---70,000 heliostats
  • World largest trough in commercial CSP project---8.2m
  • Lowest Levelised Cost of Electricity of USD 2.4 cents per kilowatt hour (kWh) for the 250MW photovoltaic solar panels technology and 7.3 cents per kWh (2.9 cents in daytime, and 9.2 cents in night time)

Participants in Dubai 700MW CSP Project:

  • Owner & Offtaker:Dubai Electricity & Water Authority, DEWA
  • Developer:ACWA Power
  • EPC Contractor:Shanghai Electric
  • Tower Technology:BrightSource
  • Parabolic trough tehcnology and solar field construction:Abengoa
  • OE:WorleyParsons--Advisian
  • Operator:NOMAC (An ACWA company)
  • Engineering:EA
  • Parabolic trough engineering and consultancy: Inner Mongolia Electric Power Survey & Design Institute
  • Power tower engineering and consultancy: Northwest Electric Power Design Institute
  • Power island design:East China Electric Power Design Institue
  • Trough:Abengoa
  • Tower Receiver:CMI
  • Steam turbine:Siemens

As the unique professional conference for global CSP peers focusing on MENA region,  the 4th CSP Focus MENA 2019 will be held on Jun.26-27 in Dubai again. Registration and application for speaking and exhibition are now open, Click to get brochure of CSP Focus MENA 2019 and you may enjoy early-bird price now.