Kyocera TCL Solar Inaugurates Floating Mega Solar Power Plants

Kyocera Corporation (President: Goro Yamaguchi; herein “Kyocera,”) and Century Tokyo Leasing Corporation (President: Shunichi Asada; herein “Century Tokyo Leasing”) announced Kyocera TCL Solar LLC, a joint venture established by the two companies, has completed construction of two floating mega-solar power plants at Nishihira Pond and Higashihira Pond in Kato City, Hyogo Prefecture, Japan. The plants, inaugurated in late March, will generate an estimated 3,300 megawatt hours (MWh) per year in total— enough electricity to power approximately 920 typical households*.
 
To see a video of the plant, please visit: https://www.youtube.com/watch?v=0801_K7VZGo
 
Overview of the Project in Hyogo Prefecture, Japan
Location - Two reservoirs in Kato City, Hyogo Prefecture, Japan
Operation - Kyocera TCL Solar LLC
Output - Nishihira Pond: 1.7MW; Higashihira Pond: 1.2MW (Total: 2.9MW)
Solar Modules 255-watt Kyocera modules (11,256 modules in total)
Expected annual power generation - Approx. 3,300MWh/year. Electricity generated will be sold to the local utility (The Kansai Electric Power Co., Inc.) through Japan’s feed-in-tariff system.
Start of construction - September 2014
Start of operation - March 2015
 
Features
  • Floating solar power generating systems typically generate more electricity than ground-mount and rooftop systems due to the cooling effect of the water.
  • They reduce reservoir water evaporation and algae growth by shading the water.
  • Floating platforms are 100% recyclable, utilizing high-density polyethylene, which can withstand ultraviolet rays and resists corrosion.
  • The floating platforms are designed and engineered to withstand extreme physical stress, including typhoon conditions.
* Based on average annual use of 3,600kWh per household. Source: Federation of Electric Power Companies of Japan
 
 