Page 10 - North American Clean Energy November/December 2018 Issue
P. 10

 solar energy
 A New Frontier for Solar
Utility build-transfer agreements
by Frank Shaw and Sean Shimamoto
HISTORICALLY, ELECTRIC UTILITIES IN THE U.S. HAVE BEEN BUYERS
and sellers, but not producers, of solar energy. Largely due to tax and accounting constraints, vertically integrated, regulated utilities traditionally have entered into power purchase agreements (PPAs) to procure solar energy (and wind and other renewable energy) from independent power producers (IPPs), rather than building such projects and including them in their rate base. To many utilities, this has seemed like a lost opportunity; they generally earn a return on the equity invested in power plants, transmission, and distribution lines, but not on power purchased from others.
Dramatic reductions in the installed cost of solar panels, improved efficiencies, and the looming expiration of federal tax benefits, have led to a new openness to utility- owned generation. A spate of build-transfer transactions — where the utility hires
a third-party project developer to develop and construct a project, then transfers ownership to the utility at completion — is creating new opportunities and challenges for developers, utilities, and equipment suppliers alike.
Challenges for Utility Ownership
Solar energy in the United States is heavily supported by federal income tax incentives, particularly investment tax credits (ITCs) and accelerated depreciation. These can account for nearly half of the capital cost of a solar project. IPPs are usually more efficient users of tax incentives, able to monetize such benefits early by partnering
with a tax equity investor; this lowers the IPP’s cost of capital and reduces production costs. Regulated utilities, however, may be required to spread such tax benefits out over the life of the asset under “normalization” rules, and other utility tax and accounting requirements. Because they can’t use the tax benefits upfront, regulated utilities have been at a competitive disadvantage.
The recent price declines for solar energy, however, have encouraged a number of utilities and state regulatory commissions to take a second look.
Even after applying normalization rules and other tax and accounting constraints, direct ownership of solar energy projects can be an attractive alternative in the current market. Moreover, some utilities with limited tax appetite are co-investing with a tax equity investor, often combining such structures with a build-transfer arrangement.
Build-Transfer Agreements
A build-transfer agreement (BTA) is a hybrid between an acquisition agreement
and a construction contract. The developer secures the needed land rights, permits, interconnection rights, and project contracts. When the project is “shovel ready,” the developer (or its contractor) builds the project for the utility. The utility generally takes ownership just before the project has been fully tested, commissioned, and starts commercial operation - it owns the project before it has been “placed in service”, for federal tax purposes. Thereafter, the project may be operated and maintained by the utility, the original developer, or a third party.
  BTAs are fairly common for state-owned utilities outside the United States, but
are seen less frequently in the U.S. Both developers and utilities have encountered challenges implementing the structure. However, some common themes have emerged from recent transactions.
First, obtaining necessary state regulatory approvals may take a year, or longer. While some utilities may seek to acquire fully developed projects (agreeing in advance to a detailed scope of work and equipment specification), others may be more comfortable with a less structured arrangement that allows such matters to be worked out in a co- development process, while pursuing regulatory approvals. To optimize timing, the
BTA may be signed before the project is fully developed, leaving certain features of the project to be defined later. The interconnection process, final site studies, final equipment selection, environmental permitting, and land-use approvals may run parallel with the regulatory approval process.
In such cases, the utility may seek to protect its interests — and those of its ratepayers — with cost caps or target-price contracts, pre-agreed standards
(or approval rights) for remaining development tasks, and baseline functional specifications for plant equipment and performance. These are in addition to traditional features of an acquisition agreement or construction contract (delay liquidated damages, performance tests, an extensive set of representations and warranties, and detailed closing conditions).
The lengthy regulatory approval process can create its own challenges for developers. To maintain price and schedule - and meet IRS tests for “commencement of construction” to qualify for the maximum ITC - developers may need to make early deposits to equipment vendors. They may seek compensation for going at risk for
these amounts through a signing payment, progress payments during the course of construction, or a termination fee for a busted deal.
These requests create countervailing pressures from the utility, which must decide how much it can put at risk to preserve the project timeline, and how to mitigate such risks if the project is canceled, or unexpected hitches arise in development or construction.
In a variation on this structure, the utility may agree to buy the developed project when it is shovel-ready - with required permits and land rights
in hand and after obtaining state regulatory approvals - but before construction begins. The developer would construct the project under a
 10
NOVEMBER•DECEMBER2018 /// www.nacleanenergy.com
 





































































   8   9   10   11   12